  • Connection Reform: Connections Network Design Methodology (Nov 24, Part 6)
    Nov 21 2024

    After the Connection Queue is filtered by Gate 2 (see previous episode), the Connections Network Design Methodology (CNDM) sets how the Connection Queue will be re-ordered and sorted to allocate capacity and substation connection points.

    In this episode, Brian & Damian run through step-by-step how NESO plans for this to work, alongside raising some discussion points and issues that you may want to raise in your consultation response. If you want to get your head around the CNDM consultation in 20 minutes, this episode is a great way to start.

    Links to useful reference materials:

    Reform Consultation Timeline: https://esmartnetworks.co.uk/wp-content/uploads/2024/11/Ongoing-Upcoming-Industry-Consultations-esmart-Networks.png

    6-page summary doc from ESO: https://www.nationalgrideso.com/document/316446/download

    NGESO Connection Reform web page: https://www.nationalgrideso.com/industry-information/connections/connections-reform

    Capacity Crunch: State of Play in May podcast (covering why this is needed): https://youtu.be/cH0r8iC3h7Q

    Listen to the podcast here:

    Spotify: https://ow.ly/3mFo50Ubyf4

    Apple Podcast: https://ow.ly/wQIM50UbyeK

    YouTube: https://ow.ly/wGM350UbyeN

    Web Player: https://ow.ly/yGUv50UbyeP

    YouTube: https://youtu.be/M8RFUosjs_s

    Follow us on our social media channels:

    LinkedIn: https://www.linkedin.com/company/esmart-networks/

    Instagram: https://www.instagram.com/esmartnetworks

    Twitter: https://twitter.com/esmartnetworks1

    Facebook: https://www.facebook.com/eSmartNetworks

    Más Menos
    26 m
  • Connection Reform: Gate 2 Methodology (Nov 24, Part 5)
    Nov 19 2024

    Part 5 in the Connection Reform mini-series follows Part 4 by delving into the next most important Consultation: Gate 2. The Gate 2 Methodology will govern what a project needs to do to be considered for capacity and a 'firm' connection offer.

    This is essential listening for project developers, those involved in project land acquisition, and project investors who want to understand key risks to large-scale Data Centres, Solar, Battery, and other types of projects. Gate 2 is the first step in deciding the winners and losers in the connection queue.

    Links to useful reference materials:

    Reform Consultation Timeline: https://esmartnetworks.co.uk/wp-content/uploads/2024/11/Ongoing-Upcoming-Industry-Consultations-esmart-Networks.png

    6-page summary doc from ESO: https://www.nationalgrideso.com/document/316446/download

    NGESO Connection Reform web page: https://www.nationalgrideso.com/industry-information/connections/connections-reform

    Capacity Crunch: State of Play in May podcast (covering why this is needed): https://youtu.be/cH0r8iC3h7Q

    Listen to the podcast here:

    Spotify: https://ow.ly/pokq50U9KlW

    Apple Podcast: https://ow.ly/j2BY50U9KlT

    YouTube: https://ow.ly/gtFn50U9KlU

    Web Player: https://ow.ly/nThq50U9KlS

    Follow us on our social media channels:

    LinkedIn: https://www.linkedin.com/company/esmart-networks/

    Instagram: https://www.instagram.com/esmartnetworks

    Twitter: https://twitter.com/esmartnetworks1

    Facebook: https://www.facebook.com/eSmartNetworks

    Más Menos
    24 m
  • Connection Reform: The Big Updates - New Consultations Released (Nov 24, Part 4)
    Nov 15 2024

    With a deluge of consultations and documents having just been released covering a lot more detail on how getting connected to the grid will change, Brian & Damian provide a high-level summary of all of the current consultations, what they cover, how they interlink and most importantly key deadlines.

    They then delve into the first consultation to close, CMP434, which sets the high-level framework for connection reform. This episode provides anyone with a good starting point on Connection reform and will help you make sense of everything that's going on.

    Links to useful reference materials:

    Reform Consultation Timeline: https://esmartnetworks.co.uk/wp-content/uploads/2024/11/Ongoing-Upcoming-Industry-Consultations-esmart-Networks.png

    6-page summary doc from ESO: https://www.nationalgrideso.com/document/316446/download

    NGESO Connection Reform web page: https://www.nationalgrideso.com/industry-information/connections/connections-reform

    Capacity Crunch: State of Play in May podcast (covering why this is needed): https://youtu.be/cH0r8iC3h7Q

    Listen to the podcast here:

    Spotify: https://open.spotify.com/episode/7dcNXoW21ahJa2LqrXM6jr?si=iKqrvOnHTqqjEQtFYQRySw

    Apple Podcast: https://podcasts.apple.com/gb/podcast/connection-reform-the-big-updates-new-consultations/id1609969567?i=1000677056077

    Web Player: https://esmartnetworks-the-grid.captivate.fm/episode/connection-reform-the-big-updates-new-consultations-released-nov-24-part-4-

    Follow us on our social media channels:

    LinkedIn: https://www.linkedin.com/company/esmart-networks/

    Instagram: https://www.instagram.com/esmartnetworks

    Twitter: https://twitter.com/esmartnetworks1

    Facebook: https://www.facebook.com/eSmartNetworks

    Más Menos
    25 m
  • Connection Reform Aug 24 Update Part 3
    Aug 28 2024

    Brian Moorhead, our Grid Consultancy Director, provides an update on the big topic of Connection Reform and where things are at following NGESO's formal consultation. In this condensed 15-minute episode, we focus on three key areas of concern and what's now happening regarding the next steps. Spoiler alert - there are some big issues in the current proposals!

    Links to useful reference materials:

    6-page summary doc from ESO: https://www.nationalgrideso.com/document/316446/download

    NGESO Connection Reform web page: https://www.nationalgrideso.com/industry-information/connections/connections-reform

    Capacity Crunch: State of Play in May podcast (covering why this is needed): https://youtu.be/cH0r8iC3h7Q

    Listen to the podcast here:

    Spotify: https://ow.ly/vL4v50T8ki2

    Apple Podcast: https://ow.ly/UK5o50T8khV

    YouTube: https://ow.ly/n98p50T8ki5

    Web Player: https://ow.ly/R3OI50T8khZ

    Follow us on our social media channels:

    LinkedIn: https://www.linkedin.com/company/esma...

    Instagram: https://www.instagram.com/esmartnetworks

    Twitter: https://twitter.com/esmartnetworks1

    Más Menos
    16 m
  • Connections Reform: Part 2
    Jun 12 2024

    Delve into part 2 of our connections reform recap!

    Fundamental Connection Reform to change GB's 'First come, first serve' system to 'First ready, First Connect' targets implementation from January 2025.

    This is big...it will directly or indirectly impact anyone seeking to connect to the Grid and will significantly change how many projects get connected. In this two-part episode Brian and David walk through what the current proposals are for the new system, what are the big unknowns and what should investors/developers be aware of at this stage.

    Links to useful reference materials:

    6-page summary doc from ESO: https://www.nationalgrideso.com/docum...

    NGESO Connection Reform web page: https://www.nationalgrideso.com/indus...

    Capacity Crunch: State of Play in May podcast (covering why this is needed): https://youtu.be/cH0r8iC3h7Q

    Listen to the podcast here:

    Spotify: https://lnkd.in/dwmeRVky

    Apple Podcast: https://lnkd.in/eHaUW7Ky

    YouTube: https://lnkd.in/ezhYzaRF

    Web Player: https://lnkd.in/ey9pqyKf

    Follow us on our social media channels:

    LinkedIn: https://www.linkedin.com/company/esma...

    Instagram: https://www.instagram.com/esmartnetworks

    Twitter: https://twitter.com/esmartnetworks1

    Facebook:

    Más Menos
    21 m
  • Connections Reform: Part 1
    Jun 5 2024

    Fundamental Connection Reform to change GB's 'First come, first serve' system to 'First ready, First Connect' targets implementation from January 2025.

    This is big...it will directly or indirectly impact anyone seeking to connect to the Grid and will significantly change how many projects get connected. In this two-part episode Brian and David walk through what the current proposals are for the new system, what are the big unknowns and what should investors/developers be aware of at this stage.

    Links to useful reference materials:

    6-page summary doc from ESO: https://www.nationalgrideso.com/docum...

    NGESO Connection Reform web page: https://www.nationalgrideso.com/indus...

    Capacity Crunch: State of play in May podcast (covering why this is needed): [https://youtu.be/cH0r8iC3h7Q]

    Listen to the podcast here:

    Spotify: https://ow.ly/ooES50Saz9H

    Apple Podcast: https://ow.ly/HCKH50Saza1

    YouTube: https://ow.ly/M9wO50Saz9X

    Web Player: https://ow.ly/YoEY50Saz9N

    Follow us on our social media channels:

    LinkedIn: https://www.linkedin.com/company/esma...

    Instagram: https://www.instagram.com/esmartnetworks

    Twitter: https://twitter.com/esmartnetworks1

    Facebook: https://www.facebook.com/eSmartNetworks

    Más Menos
    21 m
  • Capacity Crunch Update: State of Play in May 2024
    May 31 2024

    Brian Moorhead & David McDonald talk you through the major changes that are just around the corner for grid connections in the UK.

    For anyone with export capacity connections in the queue (connection offer accepted): we strongly recommend starting to do your homework for the recent Distribution and Transmission Networks Operators joint call to action.

    All projects are required to provide information on planning status and land rights for all export capacity grid connections (some DNOs have specified >1MW only, we recommend you clarify this if <1MW).

    Responding on time with the right information could be the difference between having 15 years added to your connection date, or having it accelerated. Export capacity for all accepted offers in the current queue is at risk.

    ➡️ Listen Now:

    Spotify: https://ow.ly/ookr50S3LuM

    Apple Podcast: https://ow.ly/AFvy50S3LuP

    YouTube: https://ow.ly/AtXZ50S3LuU

    Web Player: https://ow.ly/RARB50S3LuV

    Like and subscribe to stay tuned.

    Follow us on our social media channels:

    LinkedIn: https://www.linkedin.com/company/esmartnetworks

    Instagram: https://www.instagram.com/esmartnetworks

    Twitter: https://twitter.com/esmartnetworks1

    Facebook: https://www.facebook.com/eSmartNetworks

    Más Menos
    18 m
  • 2023 Look Back: Changes In How You get Connected
    Jan 18 2024

    2023 Grid Connections Reform Review: 2023 could have been one of the busiest years in living memory for reforms around how all types of new development connect to the Grid. In Part 1, Grid Consultancy Director Brian Moorhead and Technical Director David McDonald look back at the key changes announced throughout 2023, along with some highlights on what to look out for in 2024.

    Brian & David will be back in Part 2 to delve into some of the key items in more detail along with some expert analysis of what it means for new projects in 2024.

    ➡️Listen Now:

    Spotify: https://ow.ly/3xyc50Qs06m

    Apple Podcast: https://ow.ly/6PZr50Qs06A

    Google Podcast: https://ow.ly/hF8i50Qs06C

    Web Player: https://ow.ly/Kv8550Qs06l

    Like and subscribe to stay tuned.

    Follow us on our social media channels:

    LinkedIn: https://www.linkedin.com/company/esmartnetworks

    Instagram: https://www.instagram.com/esmartnetworks

    Twitter: https://twitter.com/esmartnetworks1

    Facebook: https://www.facebook.com/eSmartNetworks

    Más Menos
    26 m